Rip Kai Construction Update – Foundations

Encompass - Cayman Construction

The Encompass team has completed the following foundation groundwork:

  • Steel cages fabricated for piles
  • Batter Board completed
  • Piles for foundations underway
  • Pile clean up and site leveling underway
  • Steel cages for grade beam in production
  • Grade beam installation
  • All Grade beams poured

 

  • Formwork removed from grade beams
  • Grade beam installation is complete
  • Plumbing Rough-ins are completed for Slab
  • Electrical Rough-ins are completed for slab
  • Steelwork for slab
  • Slab has been poured
  • First floor CMU 90% Completed

 

To see all the Rip Kia construction updates view the project page here.